Question: You want to switch the scheduling mode for a project from scheduling from a start date to scheduling from a finish date. This action will change the default constraint from As Soon As Possible to As Late As Possible. Which dialog box should you use to make this change?

  1. Resource Information
  2. Project Information
  3. Task Information
  4. Change Working Time

Answer: The correct answer of the above question is Option B:Project Information