Question: You have noticed a pattern that the most interesting stories on the Sprint Backlog get started right away, and the least interesting stories languish or don't get done. What should you do?

  1. Use a lottery system assign each story.
  2. Share your observation with the team and invite them to own and solve the problem.
  3. During story point estimation increase the points assigned to the least interesting stories so the team can boost their velocity.
  4. Ask the Tech Lead to assign every story to a developer so they all get done efficiently and with accountability.

Answer: The correct answer of the above question is Option D:Ask the Tech Lead to assign every story to a developer so they all get done efficiently and with accountability.