Question: You have noticed a pattern that the most interesting stories on the Sprint Backlog get started right away, and the least interesting stories languish or don't get done. What should you do?
- Use a lottery system assign each story.
- Share your observation with the team and invite them to own and solve the problem.
- During story point estimation increase the points assigned to the least interesting stories so the team can boost their velocity.
- Ask the Tech Lead to assign every story to a developer so they all get done efficiently and with accountability.
Answer: The correct answer of the above question is Option D:Ask the Tech Lead to assign every story to a developer so they all get done efficiently and with accountability.