Question: You have implemented controls to mitigate the threats, vulnerabilities, and impact to your business. Which type of risk is left over?

  1. inherent risk
  2. residual risk
  3. applied risk
  4. leftover risk

Answer: The correct answer of the above question is Option B:residual risk