Question: You are working with a master project that contains subprojects, and you want to see a list of tasks on which a subproject file is dependent. How can you do this in Microsoft Project?

  1. On the **Project** tab, click **Subproject**.
  2. On the **View** tab, click **Group by**.
  3. On **Project** tab. click **Links Between Projects**.
  4. On the **View** tab, click **Filter**.

Answer: The correct answer of the above question is Option A:On the **Project** tab, click **Subproject**.