Question: You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?

  1. Must Finish On
  2. Start No Earlier Than
  3. As Soon As Possible
  4. Finish No Earlier Than

Answer: The correct answer of the above question is Option A:Must Finish On