Question: You are working on a project schedule. You need two tasks to end at the same time so that your review team can do their work on both tasks. Which link type is appropriate?

  1. Start-to-Start (SS)
  2. Finish-to-Start (FS)
  3. Start-to-Finish (SF)
  4. Finish-to-Finish (FF)

Answer: The correct answer of the above question is Option D:Finish-to-Finish (FF)