Question: Which statement about burndown and burnup charts is not true?

  1. Burndown charts show the work remaining to be done.
  2. Burnup charts show the work completed.
  3. Burndown charts are more useful than burnup charts.
  4. Agile project management tools can produce these automatically.

Answer: The correct answer of the above question is Option C:Burndown charts are more useful than burnup charts.