Question: When you create a new blank project in Microsoft Project, what is the default view?

  1. Resource Sheet
  2. Task Form
  3. Gantt Chart with Timeline
  4. Detail Gantt

Answer: The correct answer of the above question is Option C:Gantt Chart with Timeline