Question: What is the expected output of a Planning Poker meeting?
- The stories were discussed and each had a story point estimate assigned.
- The team gave feedback to the Product Owner about the acceptance criteria.
- The team decided what stories should be developed within the same sprint.
- The team made a preliminary plan for which stories will be completed in the next quarter.
Answer: The correct answer of the above question is Option A:The stories were discussed and each had a story point estimate assigned.