Question: What is the expected output of a Planning Poker meeting?

  1. The stories were discussed and each had a story point estimate assigned.
  2. The team gave feedback to the Product Owner about the acceptance criteria.
  3. The team decided what stories should be developed within the same sprint.
  4. The team made a preliminary plan for which stories will be completed in the next quarter.

Answer: The correct answer of the above question is Option A:The stories were discussed and each had a story point estimate assigned.