Question: A resource's hours have increased over the span of five days for a particular task. The duration has not changed, and the task is effort driven. What element can you add to the Task Usage view to see what has changed?

  1. Add a column for the actual duration.
  2. Add a column for the level assignments.
  3. Add a column for the Peak value.
  4. Add a column for the assignment.

Answer: The correct answer of the above question is Option C:Add a column for the Peak value.