Question: A resource is overallocated in a project. This resource is responsible for two tasks that are to happen at the same time. The first of these tasks is on the critical path. Which solution should you use to remedy the overallocation?

  1. Use the Leveling Gantt view adjust the edays field for the second task.
  2. Use the Task usage view to change the second task contour to an early Peak.
  3. Use the Task usage view to change the second task contour to a bell.
  4. Use the Leveling Gantt view adjust the edays field for the first task.

Answer: The correct answer of the above question is Option A:Use the Leveling Gantt view adjust the edays field for the second task.